Wednesday, March 16, 2011

Club Poulet...

We have gotten a lot accomplished this week. There has been a few set backs due to materials not being delivered on time but we kept finding something to do! All the footer for the house is dug and all the rebar is in place. We have started laying concrete for the footer. The back wall is finished. The septic tanks have been installed. We have started putting up the razor wire and pouring the foundation for the pump house! Also a family from TN has come down this week to bless the orphanage with chickens, so they have started the construction of the chicken coop or what we call "club poulet" :)